COSMIX Construction Projected Dates
The following start and completion dates are approximate. All work is weather and resource dependent.

 
Late Summer 2006
  • Holiday Village noise wall (Complete)
  • Southbound mainline traffic switch onto new frontage road (Complete)
  • Opening of new lanes in Fillmore to Garden of the Gods segment (Complete)
  • Demolition of buildings near Bijou interchange (Complete)
Fall 2006
  • Northbound mainline traffic switch onto new frontage road (Complete)
  • Garden of the Gods Rd. northbound on-ramp (Complete)
  • Opening of third lane northbound Woodmen Rd. to Academy Blvd. (Complete)
  • Opening of third lane southbound Woodmen Rd. to Academy Blvd. (Complete)
Winter 2006
  • Opening of Corporate Centre Dr. off-ramp (Complete)
  • Garden of the Gods Rd. southbound off-ramp (Complete)
Spring 2007
  • Shift mainline traffic from frontage roads to new pavement in the Nevada/Rockrimmon interchange area (Complete)
Summer 2007
  • Shift northbound mainline traffic from frontage roads to new pavement in the Nevada/Rockrimmon area (Complete)
  • Uintah St. noise wall (Complete)
  • Opening of third lane in Nevada/Rockrimmon area (Complete)
  • Northbound I-25 bridges over Colorado Ave. (Complete)

Oct. 2007

  • Re-Opening of the Bijou St. Bridge and interchange (Complete)
Fall 2007
  • Southbound I-25 bridges over Colorado Ave.
  • Pulpit Rock noise wall
  • Bijou St. interchange noise wall and berm
  • Uintah St. noise berm
Winter 2007
  • Mark Dabling/Rockrimmon utilities relocation
  • Opening of third lane from Colorado Ave. to Bijou St.
Dec. 31, 2007
  • Project Completion