| Late
Summer 2006 |
- Holiday
Village noise wall
(Complete)
-
Southbound mainline traffic switch onto
new frontage road (Complete)
-
Opening of new lanes in Fillmore to Garden
of the Gods segment (Complete)
-
Demolition of buildings near Bijou interchange
(Complete)
|
| Fall
2006 |
- Northbound
mainline traffic switch onto new frontage road
(Complete)
-
Garden of the Gods Rd. northbound on-ramp
(Complete)
-
Opening of third lane northbound Woodmen Rd. to Academy Blvd.
(Complete)
- Opening
of third lane southbound Woodmen Rd. to Academy Blvd. (Complete)
|
|
Winter
2006
|
- Opening
of Corporate Centre Dr. off-ramp
(Complete)
- Garden
of the Gods Rd. southbound off-ramp
(Complete)
|
| Spring
2007 |
- Shift
mainline traffic from frontage roads to new pavement in the Nevada/Rockrimmon
interchange area (Complete)
|
| Summer
2007 |
- Shift
northbound mainline traffic from frontage roads to new pavement
in the Nevada/Rockrimmon area (Complete)
- Uintah
St. noise wall (Complete)
- Opening
of third lane in Nevada/Rockrimmon area (Complete)
- Northbound
I-25 bridges over Colorado Ave. (Complete)
|
|
Oct. 2007
|
- Re-Opening
of the Bijou St. Bridge and interchange (Complete)
|
| Fall
2007 |
- Southbound
I-25 bridges over Colorado Ave.
- Pulpit
Rock noise wall
- Bijou
St. interchange noise wall and berm
- Uintah
St. noise berm
|
| Winter
2007 |
- Mark
Dabling/Rockrimmon utilities relocation
- Opening
of third lane from Colorado Ave. to Bijou St.
|
| Dec.
31, 2007 |
|