COSMIX Traffic Impacts - December 7 - through December 13, 2007 - Colorado Ave. West-bound Lane Closures - COLORADO SPRINGS (Friday, December 7) - COSMIX targets to close Colorado Avenue westbound lanes from Friday evening, Dec. 7 at 7:00 pm until Monday, Dec 10, at 5:30 am., in order to construct a manhole that needs to be located in the middle of the westbound lanes. During this time traffic will run head-to-head on the remaining two open lanes under the bridge. Drivers should consider using alternative routes.

Nighttime Closure: SB Off-Ramp Garden of Gods - COLORADO SPRINGS (Tuesday, Dec. 4) - COSMIX will close the southbound off-ramp to the Garden of the Gods this evening, Tuesday, Dec. 4th from midnight to 2:00 am. Closure will allow for work to create grooving on the concrete pavement. Grooving helps to drain water from the pavement, and makes the roadway less slippery. Overhead VMS signs will alert drivers of this short-term ramp closure. Drivers should use alternate routes.
Paving on Colorado Avenue - COSMIX crews are also planning work on Wednesday, December 5th, from 9:00 am - 3:00 pm, on eastbound Colorado Avenue. Eastbound Colorado Avenue will have one lane closures during these off-peak hours in order to allow for final paving of the eastbound side.

COLORADO SPRINGS (Friday, November 30) - COSMIX will close two lanes of northbound I-25 in the area over north Nevada (Nevada Bridge) beginning Saturday evening, December 1st at 9:30 pm ongoing through 5:30 am Monday, December 3rd. This closure will reduce I-25 to one lane northbound through this section. Drivers should anticipate additional travel time through this area, and use alternate routes or dates of travel, as possible. Lane closure work involves cutting, replacement and repaving of existing concrete road panels. Overhead highway message boards will remind drivers of this closure.

COLORADO SPRINGS (Wednesday, November 28) - The COMIX project will close all eastbound lanes on Rockrimmon Boulevard on Thursday, November 29th from 8:30 am to 4:00 pm. Traffic will run head to head on the remaining open lanes. Flaggers and patrol officers will be on hand to direct traffic.

COLORADO SPRINGS (Sunday, November 17) - The COMIX project’s closure of two lanes of northbound I-25 between Mark Dabling/Rockrimmon and North Nevada Ave that had been scheduled for late Saturday to early Monday (Nov. 19th ) was postponed. Weekend drivers did not encounter reduced highway lanes through this section.

COSMIX Traffic Impacts: - November 16 - through November 26, 2007*
I-25 Northbound 2-Lane Closure Saturday PM - Monday AM
COLORADO SPRINGS (Friday, November 16) - COSMIX will close two lanes of northbound I-25 between Mark Dabling/Rockrimmon and North Nevada Ave beginning Saturday evening, November 17th at 8:30 pm ongoing through 5:30 am Monday morning, November 19th. This closure will reduce I-25 to one lane northbound through this section. Drivers should anticipate additional travel time through this area, and use alternate routes or dates of travel, as possible. Lane closure work involves cutting, replacement and repaving of existing concrete road panels. Overhead highway message boards will remind drivers of this closure.

COSMIX Traffic Impacts: - November 9 - through November 16, 2007 - COLORADO SPRINGS (Friday, November 9) - COSMIX will close one lane (left lane) of northbound I-25, between Cimarron and Bijou, on Saturday morning from 7:00 am - 10:00 am. At this time of year, paving must be done during daytime hours to meet minimum temperature specifications for pavement quality. Attendees of the Veterans Day Parade in Downtown Colorado Springs should note this northbound one lane closure, and please plan their travel time accordingly. Parade attendees using northbound I-25 may wish to use the Nevada/Tejon interchange to get into downtown.

On I-25 northbound, between Mark Dabling and the North Nevada on-ramp, two lanes will close on Saturday night November 10th from 8:30 pm to 5:30 am for pavement panel saw cutting. Please observe traffic control signs and posted speed limits.

COSMIX Traffic Impacts Update - November 5 through November 9, 2007 - Rockrimmon/Mark Dabling Intersection Open - COLORADO SPRINGS (Monday, November 5) - The Mark Dabling and Rockrimmon intersection has opened to one lane of traffic in each direction (north and south along Mark Dabling, and east and west along Rockrimmon), during AM and PM rush hours. However, between 8:30 am- 3:30 pm, flaggers will direct alternating traffic on a single, shared lane. Expect travel delays during these flagging operations, which will run through this week and possibly into next week (Nov, 12th). Motorists should use extra caution driving though this area, for their own safety and for the safety of the work crews. Those wanting to avoid this intersection should consider alternate routes. Access to all businesses remains open. Access to I-25 northbound from the frontage road is now open. The southbound I-25 on ramp is not yet open, but motorists may continue to use the southbound ramp at Rusina Road. Work to complete the second lane in each direction along Rockrimmon and Mark Dabling will continue through November.

COLORADO SPRINGS (Friday, November 2) - The Mark Dabling and Rockrimmon intersection will open to limited access beginning Monday morning, November 5th, barring any additional unforeseen problems. One lane and restricted movements will be in place, as work continues in the area. Progress has been hampered by utility conflicts and large areas of unstable soil that has delayed paving. Crews have been working to resolve the problems by aerating, amending, and re-compacting the soil to achieve proper standards. It is crucial to resolve the soil and compaction problems so that the paving can be a quality, longer- lasting surface. These problems are creating the need for the limited re-opening of the intersection and adjacent roads, and could create continued delays. (SEE ATTACHED DETOUR MAP FOR INFORMATION)

COLORADO SPRINGS (Tuesday, October 30)- A full overnight closure of I-25 southbound at Bijou, the continued closure at the Mark Dabling and Rockrimmon intersection, lane restrictions on Colorado Ave, and various interstate lane closures are what motorists need to be aware of when driving through COSMIX construction zones this week.
(SEE ATTACHED DETOUR MAP FOR INFORMATION)

COLORADO SPRINGS (Monday, October 29) - The Rockrimmon/ Mark Dabling intersection closure has been extended four days due to unforeseen utility conflicts, including fiber optic, electric and water lines. The reopening is targeted for Monday, November 5th, prior to the early morning rush hour.
(SEE ATTACHED DETOUR MAP FOR INFORMATION)

COLORADO SPRINGS (Friday, October 26)- A full overnight closure of I-25 southbound at Bijou, the continued closure at the Mark Dabling and Rockrimmon intersection, lane restrictions on Colorado Ave, and various interstate lane closures are what motorists need to be aware of when driving through COSMIX construction zones this week.
(SEE ATTACHED DETOUR MAP FOR INFORMATION)

COLORADO SPRINGS (Friday, October 19) - A full intersection closure, one lane traffic, and various interstate lane closures are what motorists need to be aware of when driving through COSMIX construction zones this week.

Mark Dabling/Rockrimmon Intersection Closure Through November 1st

  • The Mark Dabling/Rockrimmon intersection is closed to traffic until November 1st.
  • Extensive utility work, drainage, retaining wall construction, paving, and curb and gutter work are being completed.
  • Business owners and residents who travel through the intersection regularly have a number of detour routes to choose from. All detour routes feature appropriate signage.
  • (SEE ATTACHED DETOUR MAP FOR INFORMATION)

COLORADO SPRINGS(Thursday, September 27) - A Bridge opening, lane closures, paving operations, and shoulder work are what motorists will need to be aware of when driving through COSMIX construction zones this week.

COLORADO SPRINGS (Wednesday, September 5)-COSMIX Construction Crews would like motorists to be aware of the following overnight on-ramp closure.

Police to Help Keep Trespassers Out of Bijou Construction Zone - COLORADO SPRINGS, Colo. (Aug. 31, 2007) – The COSMIX project is asking the Colorado Springs Police Department for help at keeping pedestrians and vehicles off the still-closed Bijou Street bridge.

COLORADO SPRINGS (Thursday, August 30, 2007) - COSMIX crews will take the Labor Day weekend off to minimize inconvenience to holiday travelers. Crews will return to work on Tuesday, September 4.

COSMIX Improves Access to Corporate Centre Dr., Nevada Ave.
COLORADO SPRINGS, Colo. (Aug. 27, 2007)
– COSMIX construction crews today opened major pieces of the new North Nevada/Rockrimmon interchange, completing the connection of Corporate Centre Drive to North Nevada Avenue and northbound Interstate 25.

COSMIX Traffic Impacts: August 23 through 30, 2007 COLORADO SPRINGS, Colo - (Thursday, August 23) - Corporate Drive openings, a full closure, and an ongoing traffic shift are what motorists need to keep an eye on this week when driving through COSMIX construction zones Corporate Centre Drive Openings.

COSMIX Begins Fix of “Nevada Dip” Sunday Night - Northbound I-25 to Get Nightly Facelift - COLORADO SPRINGS, Colo. (Aug. 10, 2007) – A dip on northbound Interstate 25 near the North Nevada Avenue on-ramp will get a facelift Sunday night when COSMIX construction crews begin repair work.

COSMIX Improves Access at Corporate Centre Drive - Construction Crews Open Southbound Access to Nevada Avenue - COLORADO SPRINGS, Colo.
(Aug. 7, 2007)

COSMIX Traffic Impacts:August 3rd through 9th, 2007 COLORADO SPRINGS, Colo (Friday, August 3rd) Overnight closures, a road opening, and an ongoing traffic shift are key items in COSMIX construction zones this week. Full Overnight Closures on Colorado Avenue Sunday, August 5th, 8p.m.-5a.m. Monday through Thursday 9p.m.- 5a.m.

COSMIX Construction Impacts: July 26th-August 2nd, 2007 COLORADO SPRINGS, Colo. (Thursday, July 26th) - A weekend detour, full overnight closures, and an ongoing traffic shift are priorities this week for COSMIX construction crews.

Northbound I-25 on-ramp from North Nevada Avenue (NB Entrance 148A) Weekend Detour from 8 p.m. Friday, July 27 to 5 a.m. Monday, July 30

COSMIX Construction Impacts: July 18th-July 26th, 2007 - COLORADO SPRINGS, Colo. (Wednesday, July 18th) - Full overnight closures, and various traffic shifts are just a few things that motorists will need to keep in mind when driving through COSMIX construction zones this week.

COSMIX Construction Impacts: July 6th-July 13th, 2007 - COLORADO SPRINGS, Colo. (Friday, July 6th) - Traffic impacts on I-25 will be minimal this week through COSMIX Construction Zones. As crews return to work after their 4th of July holiday, an overnight closure, and an ongoing traffic shift are two high priority projects that motorists will need to be aware of.

Holiday Traffic Reaps Benefits of June Progress - 3 Lanes Open Between Fontanero and North Academy - COLORADO SPRINGS, Colo. (July 3, 2007) – COSMIX construction crews have a gift for Colorado Springs before taking a break for the 4th of July. Motorists traveling I-25 today will find three lanes open both northbound and southbound from Fontanero Street to North Academy Boulevard.

COSMIX Construction Impacts: June 15th-June 21st, 2007 - COLORADO SPRINGS, Colo. (Friday, June 15th, 2007) – A recently opened off ramp, overnight closures, and a southbound traffic shift are just a few things that motorists should keep in mind when driving through COSMIX Construction Zones this week.

NEWS RELEASE - COLORADO SPRINGS, Colo. (June 14, 2007) – Today’s reopening of the southbound exit ramps at Bijou Street and the recent reopening of the northbound Rockrimmon Boulevard exit punctuated a May full of significant COSMIX progress on the Colorado Department of Transportation’s Interstate 25 project.

COSMIX Special Advisory: June 14th, 2007 - COLORADO SPRINGS, Colo.- Due to the unique and different design of the Bijou Intersection from I-25 Southbound, this Special Advisory is being sent out, along with a map, to help the Media and the Public better understand the new configuration of the new Bijou Southbound Off Ramp from I-25, helping to ensure a safer commute for motorists. Map of new configuration of Bijou Southbound Off-ramp

COSMIX Construction Impacts: Through June 15th, 2007 - COLORADO SPRINGS, Colo. (Wednesday, June 13th, 2007) Overnight closure on Colorado Avenue Through Thursday, June 21st, 9p.m.-5a.m.
a.. Crews are demolishing the Old Colorado Bridge over Colorado Avenue.
b.. Eastbound motorists will be detoured at Walnut Street.
c.. Westbound motorists are instructed to follow the posted detour signs.
d.. A new I-25 Southbound Bridge will be built following completed demolition of the old bridge over Colorado Avenue.

COSMIX Construction Impacts: June 12th, 2007 - COLORADO SPRINGS, Colo. (Tuesday, June 12th, 2007) - Necessary overnight work is needed on the Uintah Bridge, Weather Permitting. Overnight left lane closure on I-25 Southbound at Uintah, Tuesday, June 12th, 8:30p.m.-5:30a.m. (Weather Permitting)

COSMIX Construction Impacts: June 8th-June 14th, 2007 -COLORADO SPRINGS, Colo. (Thursday, June 7th, 2007) – Traffic shifts, an overnight closure, and the opening of a new southbound off ramp are a few items that motorists will need to keep in mind when driving through COSMIX construction zones this week.

COSMIX Construction Impacts: June 7th-June 14th, 2007 - COLORADO SPRINGS, Colo. (Thursday, June 7th, 2007) REV – Traffic shifts, an off ramp closure, and the opening of a new southbound off ramp are a few items that motorists will need to keep in mind when driving through COSMIX construction zones.

COSMIX Minimizes Impacts for Weekend Motorcycle Rally - COLORADO SPRINGS, Colo. (Tuesday, June 05, 2007) – In an effort to minimize inconvenience to the more than 800 Colorado State Harley-Davidson’s Owner Group (H O G ) motorcycle riders visiting Colorado Springs this weekend, the COSMIX Project will not have any overnight interstate lane closures during the rally from June 7 to 9.

COSMIX Construction Impacts: June 4th-June 8th, 2007COLORADO SPRINGS, Colo. (Monday, June 4th, 2007) – Lane Shifts, a Bridge Demolition, and the opening of a new Off Ramp are just a sample of what’s happening this week.

 

 


Archived News Releases:
April 20, 2007 to the beginning of the COSMIX Project
- March 2005

Click on button below for previous I-25 Web site.Link to previous I-25 Web site
 

Statewide Weather and Travel Information

Contact Webmaster
Last Modified: Mon, Jan, 07, 2008