October 2007
October marked a significant milestone on the COSMIX project, when the
Bijou bridge reopened to traffic. In addition, COSMIX crews began the
final piece of work in the North Nevada/Rockrimmon segment when the Rockrimmon/Mark
Dabling intersection was closed for reconstruction. Other progress
on the project included:
- Continued placement of architectural railings on the
Bijou bridge
- Landscaping and streetscape was completed on and near
the Bijou bridge
- Completed asphalt paving between South Nevada/Tejon
and Cimarron Street
- Utilities and drainage on the Spruce St. cul de sac
was completed
- Northbound bridge structure over Colorado Ave. was
completed
September 2007
This month, crews worked around the clock to prepare for the opening
of the Bijou bridge on October 1. Progress became visible to the traveling
public throughout the corridor when three lanes of I-25 became available
between North Academy Boulevard and Bijou Street. In addition,
crews made progress on the following:
- Completed landscaping behind the Pulpit Rock noise
wall.
- Opened three lanes north and southbound between Bijou
and Uintah Streets, allowing three lanes throughout the project between
North Academy Boulevard and Bijou Street.
- Continued placing decorative railing and light fixtures
on the Bijou bridge.
- Continued construction on the landscaping on the northwest
corner of Bijou Street and the I-25 interchange, and underneath the
Bijou bridge over Monument Creek.
- Continued construction on the I-25 bridges over Colorado
Avenue.
- Reopened the Pikes Peak Greenway Trail under the Bijou
bridge.
- Prepared for opening of the Bijou bridge.
- Completed paving one-half mile south of North Academy
Boulevard, and between the Martin Luther King bypass and Circle Drive.
August 2007
Good weather in August allowed the COSMIX Crews to make quite a bit of
progress. Some of the significant COSMIX work in August included:
- Poured concrete on the new I-25 southbound bridge
over Colorado Avenue
- Replaced road panels and bridge expansion joints on
I-25 southbound between Fontanero and Uintah streets
- Eliminated “the dip” on northbound I-25
at Nevada Avenue with a process known as “mud-jacking”
- Opened the Nevada/Corporate Drive intersection
- Began placing decorative railing on the Bijou bridge
- Installed light fixtures on the Bijou bridge
- Began construction on the aesthetic upgrades on the
northwest corner of Bijou Street and the I-25 interchange
- Began landscaping underneath the Bijou bridge over
Monument Creek
July 2007
The month of July began with a COSMIX gift to Colorado Springs.
Before the July 4th holiday, construction crews opened up the new third
lane on north and southbound I-25 between Woodmen Road and Garden of the
Gods Road, giving the traveling public three lanes all the way from North
Academy Boulevard to Fillmore Street.
In addition, crews also worked on the following:
- Switched traffic onto the new northbound I-25 bridge
over Colorado Avenue and began construction of the new southbound I-25
bridge over Colorado Avenue, including caisson drilling and retaining
wall construction.
- Continued work on the Corporate Centre Drive/Nevada
Avenue connection.
- Completed the new North Nevada Avenue alignment.
- Finished placing panels and staining noise walls at
Uintah Street and Pulpit Rock.
- Completed final striping between Woodmen Road and
North Academy Boulevard.
- Continued construction to repair concrete panels and
bridge joints between Fontanero and Uintah Streets.
- Continued work on the Bijou bridge including:
- Completed paving of the northbound on and off-ramps
- Completed placement of the bridge deck over Monument
Creek and the Union Pacific Railroad
- Completed 75 percent of the sidewalk and median concrete
work
- Completed the concrete staining of the abutments and
pier columns
- Began architectural stone veneer installation and
painting of the decorative railings
June 2007
June 30 marked the two-year anniversary for construction on the
COSMIX project. With two years of construction behind us and only six
months left on the project, crews made some very visible progress in June,
to include:
- Completed concrete staining on most of the North Nevada/Rockrimmon
interchange.
- Completed the Pulpit Rock noise wall.
- Opened the third lane southbound between Nevada Avenue
and Fillmore Street.
- Poured the concrete median and sidewalks for the Bijou
bridge over I-25.
- Poured two of the four deck sections of the Bijou
bridge over Monument Creek and the Union Pacific Railroad.
- Re-opened the southbound I-25 off-ramp at Bijou Street.
- Paved the northbound on and off-ramps for the Bijou
interchange.
- Completed the reinstallation and rehabilitation of
the Works Progress Administration (WPA) wall along Monument Creek near
Downtown.
- Shifted traffic onto the new portions of the I-25
bridges over Colorado Avenue and the Midland Trail.
- Completed roadway work on the west side of the Bijou
bridge.
May 2007
Several major milestones were completed in May, most notably, both north
and southbound I -25 were taken off the frontage roads and put back onto
the elevated interstate lanes in the Nevada/Rockrimmon area. It took just
less than a year to complete the 2.5 miles of new interstate lanes, eight
new bridges, and 1.8 miles of retaining walls associated with the interstate
in this area. Some of the significant COSMIX work in May included:
- Shifted southbound onto the new interstate in the Nevada/Rockrimmon
area on May 4.
- With the southbound traffic shift, the outdated left-hand
interstate exit to North Nevada Avenue was permanently eliminated and
replaced with a right hand exit.
- Demolished the old northbound I-25 bridge over the
former southbound exit to North Nevada Avenue.
- Shifted northbound I-25 traffic onto the new northbound
interstate in the Nevada/Rockrimmon area on May 24.
- Poured the remaining two bridge monuments on the east
side of the Bijou bridge.
- Paved northbound I-25 over the Monument Creek and the
Works Progress Administration (WPA) Wall.
- Reconstructed and reopened the entry to the parking
lot of the Bijou Street Denny’s in less than two weeks.
- Began placing noise wall panels for the Pulpit Rock
neighborhood sound barrier.
April
2007
Throughout April crews worked to complete the southbound mainline in the
North Nevada/Rockrimmon segment in anticipation of shifting traffic off
the frontage road and onto the new interstate lanes in early May. Other
significant COSMIX work in April included:
- Poured the last of twelve bridge decks in the North
Nevada/Rockrimmon segment on April 6.
- Placed the remaining Bijou bridge girders over Monument
Creek and the Union Pacific Railroad.
- Poured two of the four Bijou bridge monuments.
- Poured the northbound I-25 bridge deck over Colorado
Avenue.
- Closed Bijou Street from I-25 to Spruce Street to
begin raising the grade for the Bijou bridge.
- Began the rehabilitation of the northbound Midland
Bridge deck.
- Demolished the remainder of the old northbound I-25
bridge over Monument Creek in the North Nevada/Rockrimmon segment.
- Completed pouring the southbound mainline between
the bridges in the North Nevada/Rockrimmon segment.
March 2007
Progress has begun to visibly accelerate in the Colorado Avenue to Bijou
Street segment with dramatic changes to the corridor’s appearance.
Some of the significant COSMIX work in March included:
- Placed the girders for the Bijou Street bridge over
I-25 and poured the bridge deck.
- Constructed the north and southbound I-25 lanes under
the Bijou Street bridge.
- Shifted northbound I-25 traffic under the new Bijou
Street bridge.
- Began the demolition of the south half of the Cimarron
Street bridge over Conejos Street and the UPRR.
- Finished pouring piers for the Bijou bridge over Monument
Creek and the UPRR.
- Placed girders for the northbound I-25 bridge over
Colorado Avenue.
- Placed caissons and columns for the Pulpit Rock noise
wall
- Poured the northbound bridge deck over Monument Creek
in the Nevada / Rockrimmon area.
COSMIX construction crews reached 40 percent completion
on the Bijou Street Interchange last week, when traffic on north and southbound
Interstate 25 was shifted onto the new concrete lanes under the Bijou
Street bridge. The shift marked the second major milestone in the Bijou
segment. The first milestone was accomplished earlier in March, when crews
set girders for the Bijou Street bridge over I-25.
February 2007
Construction crews received a reprieve from the unusual amounts of snow
in January and February as temperatures began to warm up. Although
the snow and cold temperatures returned mid-February, workers made significant
progress in the Colorado Avenue to Bijou Street segment and the Nevada/Rockrimmon
segment. Some of the significant COSMIX work in February included:
- Shifted northbound I-25 traffic over
the Midland bridge to the west to allow for the northbound deck rehabilitation.
- Began placing the northbound retaining
wall between Colorado Avenue and Bijou Street.
- Continued with the demolition of the
Bijou bridge over Monument Creek and the Union Pacific Rail Road.
- Poured the center piers and placed the
abutment panels for the Bijou bridge over I-25.
- Opened the southbound I-25 off-ramp to
Garden of the Gods road in its final configuration.
- Re-striped north and southbound I-25
from North Nevada Avenue to Woodmen Road to accommodate the opening
of the southbound auxiliary lane from Woodmen Road to Corporate Centre
Drive.
- Opened the southbound off-ramp to Corporate
Centre Drive.
- Poured the I-25 bridge decks over the
Rockrimmon Boulevard extension.
- Poured the southbound I-25 bridge deck
over Monument Creek in the Nevada/Rockrimmon area.
- Refreshed the striping throughout the
corridor several times after the last few winter storms began to deteriorate
the pavement markings.
January 2007
January marked the start of construction on the Bijou bridge.
Despite the snow and cold temperatures, crews moved ahead on the demolition
of the bridge over I-25 and over Monument Creek and the Union Pacific
Rail Road.
Highlighted below are some of the other areas
where crews made progress:
- Continued work on the north and
southbound I-25 bridges over Monument Creek, Nevada Avenue, Rockrimmon
Boulevard, Mark Dabling Boulevard and the Union Pacific Rail Road.
- Continued construction on northbound
I-25 over Colorado Avenue.
- Completed rehabilitation work on
the southbound bridge over the Midland Trail.
- Completed demolition of the Bijou
bridge over I-25.
- Began demolition of the Bijou bridge
over Monument Creek and the Union Pacific Rail Road (40 percent complete).
- Continued work on the caissons
for the Monument Valley Park Noise Walls.
- Began placing precast columns for
the Monument Valley Park Noise Walls.
COSMIX
Progress for 2006
COSMIX
Progress for 2005
|