COSMIX Progress in 2006 from December
back to January
December 2006
Snow, snow, and more snow summarize the conditions that COSMIX
crews competed against to complete work during December. Despite
the blizzards and cold temperatures, crews were able to complete a substantial
amount of work:
- Continued concrete staining on the north
and southbound frontage road bridges over Mark Dabling Boulevard and
the Union Pacific Railroad.
- Completed the placement of girders for
the new north and southbound I-25 over Monument Creek, Rockrimmon Boulevard,
Mark Dabling Boulevard and the Union Pacific Railroad.
- Continued construction of the I-25 bridges
over Colorado Avenue.
- Completed bridge decks for the new southbound
I-25 over Nevada Avenue and the Midland Trail.
- Completed caissons for Monument Valley
Park noise walls.
- Completed concrete and asphalt paving
for northbound I-25 at Garden of the Gods Road and moved traffic to
the west.
- Completed guard rail and final alignment
striping in the Woodmen to Academy segment.
- Opened the third southbound lane between
N. Academy Boulevard and Woodmen Road.
- Began poured-in-place concrete barrier
on the southbound Garden of the Gods off-ramp.
- Completed curb, gutter and sidewalks
at the northbound Garden of the Gods on-ramp.
- Constructed temporary southbound I-25
off-ramp to Pikes Peak Avenue for a detour route when the Bijou Street
bridge and interchange closed January 3, 2007.
November 2006
November’s cold temperatures didn't’t slow down construction
this month. With only a little over a year of construction left on the
COSMIX project, Rockrimmon Constructors moved full speed ahead with their
construction schedule. COSMIX accomplished the following during
November:
- Placed girders for the new I-25 bridges over the Midland
Trail, Monument Creek in the Nevada / Rockrimmon area, and over the
southbound off-ramp to Nevada Avenue.
- Installed curb, gutter and sidewalk and paved the new
Corporate Drive extension.
- Finished removing portions of the Work Progress Administration
(WPA) walls to allow for construction. These portions will be replaced,
stone by stone, once the construction is complete.
- Placed the abutment supports for the northbound I-25
bridge over Colorado Avenue.
- Completed paving southbound I-25 between Nevada and
Cottonwood Creek and shifted northbound traffic onto the new southbound
lanes.
- Completed erecting the retaining walls for the new Rockrimmon
Boulevard extension
- Demolished the Liquor Store on Colorado Avenue and two
smaller buildings on Cucharras Street.
- Drilled and poured caissons for the noise wall at Uintah.
October 2006
Despite the blizzard in October that impacted
construction, crews were able to open the northbound third lane from Woodmen
to Academy. Below are a few significant milestones that were
reached on the COSMIX Project in October:
- Northbound lanes of I-25 from Woodmen Road to
N. Academy Avenue were placed in their final configuration and opened
to the public
- Completed the 10’ by 10’ box culverts at
Popes Bluff, Rockrimmon South, Pulpit Rock and Corporate Drive
- Completed piers for north and southbound I-25 over Monument
Creek
- Completed construction of the bridge abutments and retaining
walls for north and southbound I-25 over Nevada Avenue
- Completed both north and southbound I-25 bridge demolition
over Mark Dabling and UPRR
- Began bridge demolition and widening of northbound I-25
over Colorado Avenue
- Began bridge demolition for southbound I-25 over Midland
Trail
- Placed concrete paving between Woodmen Road and Pine
Creek
- Completed pavement overlay in the Woodmen to North Academy
segment
- Numbered, removed, and stored 6,000 square feet (one
percent) of the historic Works Progress Administration (WPA) wall along
Monument Creek to accommodate bridge construction. A majority of the
wall will be reset after construction is complete.
September 2006
Despite the incredibly wet summer, a tremendous amount of work
was completed on the COSMIX Project. COSMIX crews have been working
aggressively around the clock to complete even more construction before
the snow begins to fly. Below is the work that was done in September:
- Switched northbound traffic onto the new northbound
frontage road between Garden of the Gods and North Nevada Avenue to
allow for the reconstruction of I-25
- Demolished the southbound I-25 bridge over Monument
Creek
- Began demolishing I-25 bridges over Mark Dabling Boulevard
- Began raising the mainline base from North Nevada
Avenue to Woodmen Road to final grade
- Reopened the southbound off-ramp to Rockrimmon Boulevard,
SB Exit 147, for the traveling public’s beneficial use
- Began excavating a 65-foot deep hole for a drainage
structure that eventually will be located under the Rockrimmon underpass
at I-25.
- Began paving third lane from Woodmen to Academy
- Began staging operations for the I-25 bridges over
Colorado Avenue
- Began construction preparations for the Uintah sound
walls
- Closed southbound I-25 Bijou on-ramp to begin utility
work and the construction of the temporary southbound off-ramp onto
Pikes Peak Avenue.
- Closed the north and southbound auxiliary lanes between
Cimarron Street and Bijou Street to begin work on shoulders
August 2006
The month of August was busy with construction activity and progress.
In addition to opening the southbound third lane between Garden of the
Gods and Fillmore, COSMIX completed the following work:
- Installed lighting on the new southbound frontage
road in the North Nevada/Rockrimmon segment.
- Switched southbound I-25 traffic onto the new southbound
frontage road to allow crews to begin construction on the new I-25 mainline.
- Constructed a temporary underpass for southbound off-ramp
to N. Nevada Avenue.
- Began installing pre-cast retaining wall panels for
the I-25 bridges over the Nevada/Corporate Drive extension.
- Started grading for northbound frontage road from
Mark Dabling to Nevada
- Seeded with natural grasses along southbound I-25
shoulder between Cottonwood and Monument Creeks.
- Completed the demolition of the Western Gas Station
and Budget Rent A Car on the west side of I-25 at Bijou Street. Removed
the fuel tanks and completed environmental remediation of Western Gas
property.
- Completed lighting and median cable guardrail installation
between Fillmore and Garden of the Gods.
- Stained the Holiday Village Noise Wall.
- Repaired drainage inlet pans and completed final grading
in alley behind Holland Park noise wall
- Installed curb and gutter at the new Rockrimmon interchange
and Corporate Drive extension.
- Installed southbound guardrail between Mark Dabling
and Garden of the Gods.
July
2006
Heavy rains in July slowed down construction and caused concrete and asphalt
paving operations to be delayed. Despite this bump in the road, Rockrimmon
Constructors still completed the following work:
- Asphalt
paving of the southbound Garden of the Gods bridge deck.
-
Began installing lighting on the new southbound frontage road in the
Nevada/ Rockrimmon area.
-
Continued concrete paving of the southbound frontage road between Cottonwood
and Monument Creeks and between the temporary southbound Rockrimmon
ramps at Rusina Road and Garden of the Gods Road
-
Began concrete paving of the southbound frontage road between Monument
Creek and Mark Dabling Boulevard.
-
Backfilled the Corporate Drive box culvert to prepare for paving.
-
Set barrier along the southbound median at Pine Creek to prepare for
interstate widening between Woodmen Road and North Academy Boulevard.
-
Completed the asphalt topcoat paving between Fillmore and Garden of
the Gods.
June
2006
More warm temperatures in June allowed the COSMIX team to focus
on concrete and asphalt paving in the North Nevada/Rockrimmon and Fillmore
to Garden of the Gods segments. In addition, crews were able to begin
prep-work in the Bijou segment. The following work took place in June:
- Began
demolition of the Western Convenience Gas Station on the west side of
I-25 at Bijou to prepare for the reconstruction of the Bijou Interchange
-
Roto-milled and began asphalt paving on I-25 between Fillmore Street
and Garden of the Gods Road
-
Began paving the southbound frontage road in concrete between Cottonwood
and Monument Creeks and between the temporary southbound Rockrimmon
ramps at Rusina and Garden of the Gods Road
-
Set pre-cast concrete wall panels for the Holiday Village noise barrier
-
Poured concrete approach slabs and bridge railing on the northbound
frontage road bridges over Mark Dabling and the UPPR
-
Began utilities relocation in preparation to construct the Pulpit Rock
neighborhood noise wall
-
Began moving dirt from the northbound east shoulder between Woodmen
Road and North Academy Boulevard in preparation for widening
May
2006
Early May’s construction activities focused on the new North Nevada/Rockrimmon
interchange, the Holiday Village and Pulpit Rock neighborhood noise wall,
and preparing for work in the Woodmen to Academy segment. During May,
the following work took place:
- The
concrete deck and the approach slabs for the northbound frontage road
bridge over Mark Dabling Boulevard and the Union Pacific railroad was
poured.
-
Partial demolition of the I-25 bridge over Monument Creek.
-
Poured VMS (electronic highway signs) caissons in the North Nevada/Rockrimmon
and Woodmen to Academy segments, as well as the concrete caissons for
the Holiday Village noise wall.
-
Began prepping the Pulpit Rock neighborhood noise wall construction
area for utilities relocation
-
Began proofrolling and trimming of the southbound Collector-Distributor
frontage road, the final stage before concrete paving.
April
2006
As the temperatures in April went up, so did the construction activities.
The work in April marked the start of what will be the busiest construction
season of project. This month, crews continued to focus their efforts
on the North Nevada/Rockrimmon segment and returned to complete the Fillmore
to Garden of the Gods segment. April’s work in the North Nevada/Rockrimmon
segment included:
- Completed
utility work along westbound Rockrimmon Boulevard and moving traffic
back to its original configuration.
-
Constructing the northbound I-25 detour onto the new frontage road bridge
over Monument Creek.
-
Poured the floor and began the walls of the Corporate Drive Box Culvert
structure
-
Placed girders on the northbound frontage road bridge over Mark Dabling.
-
Poured VMS (electronic highway sign) caissons.
-
Began partial demolition of the northbound I-25 bridge over Monument
Creek.
On
the south end of the project, crews continued work on relocating the gas
line near the future Holiday Village noise wall.
March 2006
After a cold snap in February, March’s warm temperatures gave the
COSMIX team an opportunity to remain on schedule in the North Nevada /Rockrimmon
segment of the project. Typically, weather can severely impact schedule
this time of year. Construction in this segment continues to focus on
the northbound and southbound frontage roads and bridges over Monument
Creek, Mark Dabling Boulevard and the Union Pacific Railroad. However,
work has now started with the foundations and piers for the I-25 mainline
bridges over Monument Creek as well.
During
March, work in the North Nevada/Rockrimmon segment included:
-
Pouring curb on the north and southbound frontage road bridges over
Monument Creek
-
Setting retaining walls on the north and southbound frontage road bridges
over Mark Dabling Boulevard and the Union Pacific Railroad (UPRR)
-
Drilled and poured caissons for the north and southbound I-25 bridge
over Monument Creek
-
Completed the scour wall for the Corporate Drive Box Culvert
-
Constructed abutments for the north and southbound frontage road bridges
over Mark Dabling Boulevard and the UPRR
-
Paved an off-ramp detour to southbound Nevada to accommodate work on
a box culvert
-
Placed girders for the southbound frontage road bridge over Mark Dabling
Boulevard
- Constructed
10 of the 12 caissons and columns for the northbound I-25 bridges over
Monument Creek.
-
Constructed 6 of the 12 caissons and columns for the southbound I-25
bridges over Monument Creek.
Further
south, the COSMIX team put the finishing touches on the Holland Park noise
barrier and started work on the Holiday Village noise barrier.
Work
in the Fillmore to Garden of the Gods segment included:
-
Seeding the slope against the Holland Park neighborhood noise wall
-
Began relocating a gas line near the future Holiday Village neighborhood
noise wall
February
2006
February was filled with work in the North Nevada/Rockrimmon segment
of the project, with major effort focused on the frontage road bridges
over Monument Creek, Mark Dabling Boulevard and the Union Pacific Railroad.
The decks for north- and southbound bridges over Monument Creek were poured.
In addition, all of the piers for the north- and southbound frontage roads
over Mark Dabling and the Union Pacific Railroad were completed and the
girders are schedule for placement in March.
As
part of the work in the Rockrimmon area, the southbound on- and off-ramps
at Rockrimmon Boulevard were moved one-half mile south, connecting to
Tech Center Drive, to prepare for the construction of the southbound frontage
road. The northbound off-ramp to southbound Nevada Avenue was also closed
to begin excavation for a box culvert.
In
the Fillmore to Garden of the Gods segment, the design
of the Holiday Village noise wall was completed and work is scheduled
to start on the wall in March. Further north, detour paving was completed
to switch southbound I-25 traffic onto the new concrete pavement near
the Rockrimmon Boulevard exit. Detour paving was also completed to switch
southbound I-25 traffic toward the median from Cottonwood Creek to the
southbound Nevada Avenue off-ramp.
January 2006
The year 2006 started with a heavy construction schedule, which was only
a glimpse into what the next eleven months would be like for the busiest
year on the COSMIX project.
The North Nevada/Rockrimmon segment
would see the most construction with work on the frontage road bridges
over Monument Creek continuing with the completion of piers and the placement
of girders. Piers for the frontage road bridges over Mark Dabling Boulevard
and the Union Pacific Railroad were also completed and girders will be
placed in the coming months. Traffic on southbound I-25 was shifted to
the east from Cottonwood Creek to just north of the southbound Nevada
Avenue off-ramp.
In mid-January, the northbound I-25 ramp
to southbound Nevada Avenue was closed to begin work that eventually will
connect North Nevada Avenue to Corporate Drive.
Finally, in the Fillmore to Garden
of the Gods segment, southbound traffic was shifted to the inside
onto the new concrete pavement to allow the outside southbound lanes to
be paved.